A: Traffic will be limited to a single lane over the Route 9D structure until late October, according to the state Department of Transportation. As part of the $2.2 million project between Cold Spring and Garrison, workers are replacing joints, adding a drainage system, repairing piers and abutments, sealing the deck and paving the approaches.

Approaching the bridge from the south (Photo by Michael Turton)
Have a question we can answer? Email: [email protected].
Thanks, Mike. Good to know that we need to plan for extra time or a detour only until about October!